Wednesday, August 01, 2007

Steel decking with rebar gets laid this week.

100'x 100' Sub cellar parking level with decking and re-bar installation over steel I-beam grid. Passenger elevator shaft has been left open. They will bring in a large crane to remove the forklift parked at the bottom. Next step will be to pour the concrete.